Skip to main content
BIM Execution Planning

5.12
Information Management Risk Register

Documents the register of information management risk items for the project.

  1. Risk Register: Table of the primary risks that impact the information management practices on the project.
  2. Risk Name: The name of the risk.
  3. Risk Description: A description of the risk.
  4. Probability: The probability that a risk may occur on the project.
  5. Consequence: The consequences that may occur if the risk is encountered.
  6. Mitigation Methods: A description of the mitigation method(s) to be used to mitigate or manage the risk.
  7. Risk Category: A category for various types of risk, e.g., training, information approval, or information sharing.
  8. Risk Status: The status of addressing the risk, e.g., open, closed, etc.
  9. Responsible Party: The lead party responsible for managing the specific risk.
National BIM Standard-United States® (NBIMS-US™) Version 4

The NBIMS-US™ v4 is a consensus-based national-level standard focused on defining standard approaches and guidelines to defining requirements, planning BIM adoption, and exchanging information between project team members. MORE