BIM Execution Planning
5.12Information Management Risk Register
Documents the register of information management risk items for the project.
- Risk Register: Table of the primary risks that impact the information management practices on the project.
- Risk Name: The name of the risk.
- Risk Description: A description of the risk.
- Probability: The probability that a risk may occur on the project.
- Consequence: The consequences that may occur if the risk is encountered.
- Mitigation Methods: A description of the mitigation method(s) to be used to mitigate or manage the risk.
- Risk Category: A category for various types of risk, e.g., training, information approval, or information sharing.
- Risk Status: The status of addressing the risk, e.g., open, closed, etc.
- Responsible Party: The lead party responsible for managing the specific risk.